Ti = Force Majeure
1.Ti = Definition of Force Majeure
1.sec = The term “Force Majeure,” as used in this Agreement, means causes or events beyond the reasonable control of, and without the fault or negligence of the party claiming Force Majeure, including, without limitation, acts of God, sudden actions of the elements such as floods, earthquakes, hurricanes, wind speeds in excess of safe working limits, or tornadoes; sabotage; vandalism beyond that which could reasonably be prevented by Seller; terrorism; war; riots; fire; explosion; severe cold or hot weather or snow or other extreme or severe weather conditions; blockage, insurrection, strike, slow down, or labor disruptions (even if such difficulties could be resolved by conceding to the demands of a labor group); and requirements, actions or failures to act by Transmission System Operator, but only if such requirements, actions or failures to act prevent or delay performance; the adoption or change in any rule or regulation or judicial decision lawfully imposed by Federal, state, or local government bodies; inability, despite due diligence, to obtain required licenses, permits, or approvals for the construction and operation of the Facility under the terms of this Agreement; and the mechanical or equipment breakdown of the Grid to the extent not caused by the party claiming the Force Majeure. The term “Force Majeure” does not include any full or partial curtailment in the electric output of the Facility that is caused by or arises from the act or acts of any third party, including, without limitation, any vendor, materialman, customer, or supplier of Seller, unless such act or acts is or are itself or themselves excused by reason of Force Majeure. The term “Force Majeure” does not include any full or partial curtailment in the electric output of the Facility that is caused by or arises from a mechanical or equipment breakdown of the Facility, or fires, explosions, or other mishap or events or conditions attributable to normal wear and tear or flaws related to the Facility, unless caused by a Force Majeure event specifically listed in the first sentence of this Section 14(a).
2.Ti = Applicability of Force Majeure
2.0.sec = Neither Party shall be responsible or liable for any delay or failure in its performance under this Agreement due to conditions or events of Force Majeure (except that any and all obligations to pay money shall not be delayed or excused by conditions or events of Force Majeure), provided that:
2.1.sec = the non-performing Party gives the other Party prompt written notice describing the particulars of the occurrence of the Force Majeure;
2.2.sec = the suspension of performance is of no greater scope and of no longer duration than is required by the Force Majeure;
2.3.sec = the non-performing Party proceeds with reasonable diligence to remedy its inability to perform and provides weekly progress reports to the other Party describing actions taken to end the Force Majeure; and
2.4.sec = the non-performing Party shall provide written notice of its ability to resume performance of its obligations under this Agreement.
2. = [G/Z/ol/s4]
3.Ti = Limitations on Effect of Force Majeure
3.sec = In no event will any delay or failure of performance caused by any conditions or events of Force Majeure extend this Agreement beyond its stated term. In the event of any delay or failure of performance caused by conditions or events of Force Majeure, which would otherwise constitute an Event of Default pursuant to Section 10, the cure provisions of Section 10 shall not apply and such delay or failure of performance, if not previously cured, shall be extended day-for-day by the event of Force Majeure; provided that such delay or failure shall become an Event of Default one (1) year from the date of notice provided for in Section 10. The other Party may, at any time following the end of such one-year period, terminate this Agreement upon written notice to the affected Party, without further obligation by the terminating Party except as to costs and unpaid balances incurred prior to the effective date of such termination. The other Party may, but shall not be obligated to, extend such one year period, for such additional time as it, at its sole discretion, deems appropriate, if the affected Party is exercising due diligence in its efforts to cure the conditions or events of Force Majeure.
4.Ti = Delays Attributable to BPA
4.sec = Seller shall be excused from delays in meeting performance deadlines under this Agreement, on a day-for-day basis, for any delays attributable to BPA, including, without limitation, delays in BPA obtaining any required permits, consents, or approvals and agreements, including, without limitation, the Delivery Arrangements Agreement, from governmental authorities or third parties required for BPA to perform its obligations under this Agreement. Seller shall provide BPA with timely written notice that a delay allegedly attributable to BPA has occurred or is expected to occur. The notice shall specify the length of any extension to a performance deadline to which Seller feels entitled.
= [G/Z/ol/4]