Ti = Bonus Pool Plan
0.sec = The General Contractor will establish a Bonus Pool program offering every Subcontractor a cash incentive for achieving the Project Goals outlined below.
1.0.sec = The Project Goals are:
1.1.sec = The project is completed by the Completion Date;
1.2.sec = There are no unresolved claims by any subcontractor for interference or damage by any other subcontractor or contractor; and
1.3.sec = There have been no accidents which have caused more than {WorkDaysLost.#} work days to be lost.
1. = [G/Z/ol-a/s3]
2.sec = If all of the Project Goals are achieved, the General Contractor will pay to each Subcontractor, in addition to each Subcontractor’s normal compensation, a bonus of {BonusToSubcontractor.%} of the Subcontractor’s adjusted contract sum.
= [G/Z/ol/s2]